MAWSS has many construction projects and other capital improvement projects. From repairs to new expansions of infrastructure and more, check here for a list of current and upcoming projects.
A new sludge dewatering facility is being constructed at the C.C. Williams Wastewater Treatment Plant. The new facility will have greater capacity, reliability and efficiency than the existing older facility. Increased dewatering efficiency means reduced costs in hauling sludge. Sludge from both the
The E.M. Stickney Water Treatment Plant, initially constructed in 1942 and is Mobile's primary drinking water treatment facility, will be getting a complete overhaul of all electrical systems. This project includes the installation of new generators providing greater electrical capacity and
The Magnolia Grove Lift Station and Force Main is being constructed to reduce sanitary sewer overflows (SSOs) in the area resulting from blockages in the long gravity sewer crossing under the golf course.The project started on April 11, 2022.The anticipated completion date is May 6,
MAWSS is rehabilitating the 50 million gallon reservoir at the E.M. Stickney Water Treatment Plant.Start Date: May 23, 2023Completion Date: May 19, 2025Cost: $13.9 MillionAn aerial view of the site of the reservoir rehabilitation project.Haren Construction continues work on the
This project is to redirect LS051 flow through a larger carrier pipe and different discharge point to help mitigate wet weather SSO's. Project #: 1025625Cost: $1,342,041Estimated Completion Date: June 26, 2024Click on the map to the right to view a
This project is to redirect LS089 flow through a larger carrier pipe and different discharge point at LS189 to help mitigate wet weather SSO's. Project Cost: $1,353,250.00Estimated Completion Date: May 2024
A new trunk sewer is being constructed parallel to the existing Eslava Creek trunk sewer for the purpose of reducing wet weather SSOs along the Eslava Creek trunk sewer. The new pipeline will add capacity for conveying wastewater from near Mt. Island Drive to a new pump station at Bucker Rd. The
Two 10 million gallon tanks will be constructed south of Norton's Lane and east of Navco Road to alleviate wet weather SSOs that occur near the Eslava Creek Trunk Sewer. The facility will also include a pump station constructed at 1272 Bucker Rd.Cost of Project:
MAWSS is rehabilitating a 48" wastewater forcemain by Eslava Creek via sliplining. The involves installing a slightly smaller carrier pipe into the forcemain.Estimated Cost: $4,256,208.00Estimated Completion: December 2025.
A new force main will be constructed from the Crenshaw St. Lift Station to the newly completed Three Mile Creek Trunk Sewer.The force main will be routed to the north from the Crenshaw St. Lift Station on the following streets: Crenshaw, Emogene, Mohawk, Dauphin, Upham, and Levert. This project
This 32-year old building is being completely modernized with new equipment to dewater sludge produced during the process of converting raw water to potable water.Cost of Project: $9.3 MillionEstimated Completion Date: July 2023An aerial view of the H.E. Myers Water Treatment
MAWSS is renovating the old EMA Building on McGregor Avenue into its new Central Laboratory and Pretreatment Department.Project Cost: $2.4 millionConstruction Start Date: August 2022Construction Completion Date: July 2023
This project provides redundancy, longevity and added capacity to a 50-year old critical force main that runs parallel to I-10from Eslava Creek to the Williams WWTP. Phase I is the final phase of 4 phases of constructing nearly 4.5 miles of pipeline.Cost of Phase I = $14.2
The Island Road Elevated Storage Tank is getting painted for structural longevity.Start Date: November 9, 2022Anticipated Completion Date: May 6, 2023Cost: $0.9 millionClick the map below to view a larger version.
An existing depressed gravity sewer main under the golf course is defective and prevents proper cleaning of the sewer. It is being replaced with a force main to prevent blockages and resulting sanitary sewer overflows.Cost: $1.3 MillionStart Construction: March 30, 2022Completion: January
A project is underway at MAWSS to replace six underground fuel storage tanks with aboveground tanks.The tanks are at various locations within MAWSS facilities. When the project is completed, all of MAWSS'fuel tanks will be above ground.Cost of Project: $1.55 millionEstimated
The new Augusta Lift Station Force Main will allow the Augusta Lift Station to be upgraded in capacity for the purpose of serving additional customers upstream of the lift station. Streets impacted by the project include Augusta Dr. N. and Aiken Way.Cost: $1.1 MillionCompletion: September
This project provides redundancy, longevity and added capacity to a 50-year old critical force main that runs parallel to I-10 from Eslava Creek to the Williams WWTP. Phase 2 is one of 4 phases in constructing nearly 4.5 miles of pipeline.Cost of Phase 2 = $15.9 MillionEstimated
The Big Creek Lake Boat Wash Facility is a necessary means of preventing invasive species from being transported into Big Creek Lake from other water bodies. All boats must be washed at the Facility before entering Big Creek Lake. Facility will include two lanes for boat washing, a guard house and
The influent screening and grit removal facilities are being replaced at the Smith WWTP which was originally constructed in 1947. The new facilities will be more reliable, provide for more efficient treatment and better accommodate higher flows into the plant during rainfall.Cost: $10.1
Construction of 3 earthen wastewater equalization basins with associated piping and flow control structures to temporarily retain flows diverted from the lift station during high flow events commonly associated with rainfall inflow and infiltration (I&I). Estimated completion - Winter
Construction of new plant headworks and primary clarifiers to provide increased capacity and process efficiencies of treatment plant. Estimated completion - Winter 2018- Construction Costs: $7,930,000- Location: C.C. Williams WWTP
Construction of piping and flow control structures to allow for the bypassing of station in cases of emergency. Estimated completion - Wnter 2018- Construction Costs: $745,743- Location: Eslava Creek Lift Station
Construction of valving and new piping necessary to allow for the abandonment and filling of existing 30” water line with grout. Estimated completion - Fall 2017- Construction Costs: $474,195- Location: Springhill Area
Construction of approximately 3,300 linear feet of new 18” waterline to replace an existing waterline that has failed and construction of bypass connections for utilization during emergencies. Estimated completion - Fall 2017
Construction associated with the relocation of water lines and sanitary sewer rehabilitation due to utility conflicts at 46 locations in MAWSS service area. Estimated completion - Fall 2017.Starting Costs: $1,768,680Total Costs: $2,100,0000Contractor: REV Construction
Construction of 2,300 feet of 12” sewer force main to replace damaged 24” gravity main; replacement of 100 feet of 24” gravity main and replacement of sewer manhole. Estimated completion - Fall 2017Construction costs: $1,350,000Location: Driftwood Drive
Construction of approximately 350 feet of 8” sanitary sewer pipe to replace an existing line that has deteriorated. Estimated completion - fall 2017Construction Costs: $110,000Location: Hillcrest Shopping Center Contractor: Ballcon, Inc.
This project involves the installation of approximately 220 LF of 8” sewer pipe utilizing “Pipe Bursting” method to replace existing deteriorated pipe. Estimated completion - summer 2017Construction Costs: $140,000Contractor: Ballcon, Inc.
Installation of surge tank, piping and associated equipment to minimize transient pressure in force main downstream of pump station. Estimated completion - Winter 2018Construction Costs: $543,000Location: Eslava Lift StationContractor: S. C. Stagner Contracting, Inc.
Replacement of sewer main of Childers Street between Riverside DriveConstruction Costs: $122,928Location: Childers StreetContractor: Construction Labor Services, Inc.
Completed - Construction of new water and sewer services and repaving of Macy Place from Government Blvd to Luling Street. Estimated Completion - summer 2017Construction Costs: (Revised Contract Amount): $262,591Location: Macy PlaceContractor: Ballcon, Inc.
Installation of new bar screens to remove solids from waste stream in advance of intake by pumps. Estimated completion - Summer 2017Construction Costs: $773,900Location: Virginia Street Contractor: J. S. Haren, Inc.
Construction of a second lime silo and associated appurtenances to provide redundancy to lime feed system utilized for raw water treatment. Estimated completion - Summer 2017Construction Costs: $826,348Contractor: The Creel Company
Construction Costs: $543,531Contractor: Ballcon, Inc.
Construction of approximately 3,300 linear feet of new 18” waterline to replace an existing waterline that has failed and construction of bypass connections for utilization during emergencies. Estimated completion - Fall 2017Construction Costs: $3,071,089.41 (Part A, Option
Construction of new sewer mains to replace deteriorated piping on Virginia St., Everett St., and Cottage Drive. Estimated completion - Fall 2017Construction Costs: $1,132,072.77Location: Virginia St./Everett St/Cottage DriveContractor: Frank Turner Construction Co., Inc.
- Construction associated with the relocation of water lines and sanitary sewer rehabilitation due to utility conflicts at 46 locations in MAWSS service area. Estimated completion - Fall 2017.- Costs
- Construction Costs: $826,348- Location: Stickney WTP
- Construction Costs: $2,500,000- Location: Gaillard P.S.
- Construction Costs: $3,071,000- Location: Causeway
- Construction Costs: $773,900- Location: Virginia Street Lift Station
- Construction Costs: $3,125,771.76- Location: Forest Hill Office
- Construction Costs: $230,000- Location: Schillinger Road
- Construction Costs: $320,911- Location: Macy Place
- Construction Costs: $1,290,803- Location: Bizzel Avenue
- Construction Costs: $2,144,681.84- Location: Owens Street
MAWSS Park Forest Plaza
4725 Moffett Road
Mobile, AL 36618