Skip to main content

Projects

MAWSS has many construction projects and other capital improvement projects. From repairs to new expansions of infrastructure and more, check here for a list of current and upcoming projects.

Construction Projects

C.C. Williams Wastewater Treatment Plant Dewatering Facility

A new sludge dewatering facility is being constructed at the C.C. Williams Wastewater Treatment Plant. The new facility will have greater capacity, reliability and efficiency than the existing older facility. Increased dewatering efficiency means reduced costs in hauling sludge. Sludge from both the

View

Capital Projects

Stickney Water Treatment Plant Electrical Upgrades

The E.M. Stickney Water Treatment Plant, initially constructed in 1942 and is Mobile's primary drinking water treatment facility, will be getting a complete overhaul of all electrical systems. This project includes the installation of new generators providing greater electrical capacity and

View

Construction Projects

Magnolia Grove Lift Station & Force Main

The Magnolia Grove Lift Station and Force Main is being constructed to reduce sanitary sewer overflows (SSOs) in the area resulting from blockages in the long gravity sewer crossing under the golf course.The project started on April 11, 2022.The anticipated completion date is May 6,

View

Capital Projects

Stickney Water Treatment Plant 50 Million Gallon Reservoir Rehabilitation

MAWSS is rehabilitating the 50 million gallon reservoir at the E.M. Stickney Water Treatment Plant.Start Date: May 23, 2023Completion Date: May 19, 2025Cost: $13.9 MillionAn aerial view of the site of the reservoir rehabilitation project.Haren Construction continues work on the

View

Construction Projects

Mobile St LS051 Forcemain Upgrade

This project is to redirect LS051 flow through a larger carrier pipe and different discharge point to help mitigate wet weather SSO's. Project #: 1025625Cost: $1,342,041Estimated Completion Date: June 26, 2024Click on the map to the right to view a

View

Construction Projects

Baker LS089 to Augusta LS189 Forcemain Upgrade

This project is to redirect LS089 flow through a larger carrier pipe and different discharge point at LS189 to help mitigate wet weather SSO's. Project Cost: $1,353,250.00Estimated Completion Date: May 2024

View

Capital Projects

Eslava Creek Trunk Sewer Upgrades

A new trunk sewer is being constructed parallel to the existing Eslava Creek trunk sewer for the purpose of reducing wet weather SSOs along the Eslava Creek trunk sewer. The new pipeline will add capacity for conveying wastewater from near Mt. Island Drive to a new pump station at Bucker Rd. The

View

Capital Projects

Norton's Lane Severe Weather Attenuation Facility

Two 10 million gallon tanks will be constructed south of Norton's Lane and east of Navco Road to alleviate wet weather SSOs that occur near the Eslava Creek Trunk Sewer. The facility will also include a pump station constructed at 1272 Bucker Rd.Cost of Project:

View

Capital Projects

Eslava Creek 48

MAWSS is rehabilitating a 48" wastewater forcemain by Eslava Creek via sliplining. The involves installing a slightly smaller carrier pipe into the forcemain.Estimated Cost: $4,256,208.00Estimated Completion: December 2025.

View

Construction Projects

Crenshaw St. Lift Station and Force Main Upgrades

A new force main will be constructed from the Crenshaw St. Lift Station to the newly completed Three Mile Creek Trunk Sewer.The force main will be routed to the north from the Crenshaw St. Lift Station on the following streets: Crenshaw, Emogene, Mohawk, Dauphin, Upham, and Levert. This project

View

Construction Projects

H.E. Myers Water Treatment Plant Solids Handling Facility Renovations

This 32-year old building is being completely modernized with new equipment to dewater sludge produced during the process of converting raw water to potable water.Cost of Project: $9.3 MillionEstimated Completion Date: July 2023An aerial view of the H.E. Myers Water Treatment

View

Capital Projects

McGregor Avenue EMA Building Renovation

MAWSS is renovating the old EMA Building on McGregor Avenue into its new Central Laboratory and Pretreatment Department.Project Cost: $2.4 millionConstruction Start Date: August 2022Construction Completion Date: July 2023

View

Capital Projects

Eslava Creek 48-inch Sewer Force Main Replacement - Phase 1

This project provides redundancy, longevity and added capacity to a 50-year old critical force main that runs parallel to I-10from Eslava Creek to the Williams WWTP. Phase I is the final phase of 4 phases of constructing nearly 4.5 miles of pipeline.Cost of Phase I = $14.2

View

Construction Projects

Island Road Elevated Storage Tank Painting

The Island Road Elevated Storage Tank is getting painted for structural longevity.Start Date: November 9, 2022Anticipated Completion Date: May 6, 2023Cost: $0.9 millionClick the map below to view a larger version.

View

Construction Projects

Magnolia Grove Lift Station and Force Main

An existing depressed gravity sewer main under the golf course is defective and prevents proper cleaning of the sewer. It is being replaced with a force main to prevent blockages and resulting sanitary sewer overflows.Cost: $1.3 MillionStart Construction: March 30, 2022Completion: January

View

Capital Projects

Fuel Storage Tank Replacement

A project is underway at MAWSS to replace six underground fuel storage tanks with aboveground tanks.The tanks are at various locations within MAWSS facilities. When the project is completed, all of MAWSS'fuel tanks will be above ground.Cost of Project: $1.55 millionEstimated

View

Construction Projects

Augusta Lift Station Force Main Improvements

The new Augusta Lift Station Force Main will allow the Augusta Lift Station to be upgraded in capacity for the purpose of serving additional customers upstream of the lift station. Streets impacted by the project include Augusta Dr. N. and Aiken Way.Cost: $1.1 MillionCompletion: September

View

Construction Projects

Eslava Creek 48-inch Sewer Force Main Replacement – Phase 2

This project provides redundancy, longevity and added capacity to a 50-year old critical force main that runs parallel to I-10 from Eslava Creek to the Williams WWTP. Phase 2 is one of 4 phases in constructing nearly 4.5 miles of pipeline.Cost of Phase 2 = $15.9 MillionEstimated

View

Construction Projects

Big Creek Lake Boat Wash Facility

The Big Creek Lake Boat Wash Facility is a necessary means of preventing invasive species from being transported into Big Creek Lake from other water bodies. All boats must be washed at the Facility before entering Big Creek Lake. Facility will include two lanes for boat washing, a guard house and

View

Construction Projects

Wright Smith Jr. Wastewater Treatment Plant Headworks

The influent screening and grit removal facilities are being replaced at the Smith WWTP which was originally constructed in 1947. The new facilities will be more reliable, provide for more efficient treatment and better accommodate higher flows into the plant during rainfall.Cost: $10.1

View

Construction Projects

Halls Mill Creek L.S. Storm Water Attenuation Basins

Construction of 3 earthen wastewater equalization basins with associated piping and flow control structures to temporarily retain flows diverted from the lift station during high flow events commonly associated with rainfall inflow and infiltration (I&I).  Estimated completion - Winter

View

Construction Projects

Clifton C. Williams New Headworks & Primary Clarifiers

Construction of new plant headworks and primary clarifiers to provide increased capacity and process efficiencies of treatment plant.  Estimated completion - Winter 2018- Construction Costs: $7,930,000- Location: C.C. Williams WWTP

View

Construction Projects

Eslava Creek Lift Station Emergency Bypass Facilities

  Construction of piping and flow control structures to allow for the bypassing of station in cases of emergency.  Estimated completion - Wnter 2018- Construction Costs: $745,743- Location: Eslava Creek Lift Station

View

Construction Projects

Springhill 30

Construction of valving and new piping necessary to allow for the abandonment and filling of existing 30” water line with grout.  Estimated completion - Fall 2017- Construction Costs: $474,195- Location: Springhill Area

View

Construction Projects

Mobile to Spanish Fort Waterline Replacement and Upgrades

Construction of approximately 3,300 linear feet of new 18” waterline to replace an existing waterline that has failed and construction of bypass connections for utilization during emergencies.  Estimated completion - Fall 2017

View

Construction Projects

Waterline Relocation and Sanitary Sewer Rehabilitation

Construction associated with the relocation of water lines and sanitary sewer rehabilitation due to utility conflicts at 46 locations in MAWSS service area. Estimated completion - Fall 2017.Starting Costs: $1,768,680Total Costs: $2,100,0000Contractor: REV Construction

View

Construction Projects

Driftwood Drive Emergency Lift Station Repairs

Construction of 2,300 feet of 12” sewer force main to replace damaged 24” gravity main; replacement of 100 feet of 24” gravity main and replacement of sewer manhole.  Estimated completion - Fall 2017Construction costs: $1,350,000Location: Driftwood Drive

View

Construction Projects

Hillcrest Shopping Center Sewer Line Replacement

Construction of approximately 350 feet of 8” sanitary sewer pipe to replace an existing line that has deteriorated.  Estimated completion - fall 2017Construction Costs: $110,000Location: Hillcrest Shopping Center Contractor: Ballcon, Inc. 

View

Construction Projects

Emergency Cimarron Ridge Apartments Sewer Replacement

This project involves the installation of approximately 220 LF of 8” sewer pipe utilizing “Pipe Bursting” method to replace existing deteriorated pipe.  Estimated completion - summer 2017Construction Costs: $140,000Contractor: Ballcon, Inc.

View

Construction Projects

Eslava Lift Station Surge Tank Installation

Installation of surge tank, piping and associated equipment to minimize transient pressure in force main downstream of pump station.  Estimated completion - Winter 2018Construction Costs: $543,000Location: Eslava Lift StationContractor: S. C. Stagner Contracting, Inc.

View

Construction Projects

Childers Street Repairs

Replacement of sewer main of Childers Street between Riverside DriveConstruction Costs: $122,928Location: Childers StreetContractor: Construction Labor Services, Inc.

View

Macy Place Water and Sewer Services Replacement

Completed - Construction of new water and sewer services and repaving of Macy Place from Government Blvd to Luling Street.  Estimated Completion - summer 2017Construction Costs: (Revised Contract Amount): $262,591Location: Macy PlaceContractor:  Ballcon, Inc.

View

Construction Projects

Virginia Street Lift Station Bar Screens Replacement

Installation of new bar screens to remove solids from waste stream in advance of intake by pumps.  Estimated completion - Summer 2017Construction Costs: $773,900Location: Virginia Street Contractor: J. S. Haren, Inc. 

View

Construction Projects

MAWSS Lime Silo at Stickney Plant

Construction of a second lime silo and associated appurtenances to provide redundancy to lime feed system utilized for raw water treatment.  Estimated completion - Summer 2017Construction Costs: $826,348Contractor: The Creel Company

View

Construction Projects

Cypress Cove Apartments Water Main Repairs

Construction Costs: $543,531Contractor: Ballcon, Inc.

View

Construction Projects

Mobile to Spanish Fort Waterline Replacements & Upgrades

Construction of approximately 3,300 linear feet of new 18” waterline to replace an existing waterline that has failed and construction of bypass connections for utilization during emergencies.  Estimated completion - Fall 2017Construction Costs: $3,071,089.41   (Part A, Option

View

Construction Projects

MAWSS Mainline Sewer Replacement Virginia St./Everett St/Cottage Drive

Construction of new sewer mains to replace deteriorated piping on Virginia St., Everett St., and Cottage Drive.  Estimated completion - Fall 2017Construction Costs: $1,132,072.77Location: Virginia St./Everett St/Cottage DriveContractor: Frank Turner Construction Co., Inc.

View

Construction Projects

Water Main Relocation & Sanitary Sewer Rehabilitation

- Construction associated with the relocation of water lines and sanitary sewer rehabilitation due to utility conflicts at 46 locations in MAWSS service area. Estimated completion - Fall 2017.- Costs

View

Construction Projects

Lime Silo at E.M. Stickney Plant

- Construction Costs: $826,348-  Location: Stickney WTP

View

Construction Projects

Gaillard Pump Station

- Construction Costs: $2,500,000- Location: Gaillard P.S.

View

Construction Projects

Mobile to Spanish Fort Waterline Replacement

- Construction Costs: $3,071,000- Location: Causeway

View

Construction Projects

Virginia Street Lift Station Screen Installs

- Construction Costs: $773,900- Location: Virginia Street Lift Station

View

Construction Projects

Bienville Reservoir Tank Replacement

- Construction Costs: $3,125,771.76- Location: Forest Hill Office

View

Sewer Force Main from Schillinger Road East to Manhole #195

- Construction Costs: $230,000- Location: Schillinger Road

View

Construction Projects

Macy Place Water & Sewer Services & Pavement Replacement

- Construction Costs: $320,911- Location: Macy Place

View

Construction Projects

Bizzel Avenue Sewer Lift Station

- Construction Costs: $1,290,803- Location: Bizzel Avenue

View

Construction Projects

48'' Raw Water to Potable

- Construction Costs: $2,144,681.84- Location: Owens Street

View

ARCGIS Map of all Capital Projects

Today's Hours

Call Center: 8:00AM - 5:00PM

Lobby Hours (Kiosk Only): 8:00AM - 4:30PM

Find Locations

Emergencies 24/7/365

251.694.3165

Main Office Address

MAWSS Park Forest Plaza
4725 Moffett Road
Mobile, AL 36618